Details of 3rd party inspection Quality Assurance works completed / on hand

(Amount in Rs.)

Providing Project Management Consultancy for SHDP Phase-IV Works Under Kolar & Chikballapur District’s (Work Package Nos: 317, 318, 319, 320, 321, 322, 323, 324 & 325), Package No.: PMC/PH-4/BNG-IV

Estimated Cost (Lakhs) - 22412.38

Tendered cost - 22412.38

Actual date of completion- 06.10.2020

Construction of Bengaluru Dr.B.R.Ambedkar School of Economics (BASE) at Bengaluru University campus, Jnana Bharathi, Bengaluru urban District. (Buildings and Development works)-KHB

Estimated Cost (Lakhs) - 16699.51

Tendered cost - 16699.51

Actual date of completion- 21.09.2019

Project Monitoring and Quality Auditing Services for the work of Construction of Super Speciality Hospital in the premises of Gulbarga Institute of Medical Sciences at Kalaburagi -KHSDRP

Estimated Cost (Lakhs) - 12414.65

Tendere cost - 12414.65

Actual date of completion- 07.09.2019

Consultancy services for Project Management including, supervision, quality assurance, progress monitoring /reporting, measurement, billing and documentation

for the work of “Construction of 192 PC quarters at Audugodi (pkg-17), 128 PC quarters at K R Puram (pkg-18) and 64 PC + 128 SI quarters at Mysore road circle (pkg-19) under Police Gruha 2020 scheme”. pmc package – 07 - KSPH & IDCl-BNG

Estimated Cost (Lakhs) - 9268.52

Tendered cost - 9268.52 

Actual date of completion- 30.07.2019

Consultancy services for Project Management including, supervision, quality assurance, progress monitoring /reporting, measurement, billing and documentation for the work of “Construction of 132 PC+ 12 SI quarters

in Mandya & Chamarajanagar District (pkg-06) and 156 PC quarters in Mysore district (pkg-07) under Police gruha 2020 scheme”. pmc package – 03-KSPH & IDCl-MYS

Estimated Cost (Lakhs) - 4614.72

Tendered cost - 4614.72  

Actual date of completion- 09.07.2019

Project Management Consultancy for SHDP Phase-III works under BANGLORE circle, Package No.: BNG-I

Estimated Cost (Lakhs) - 19589.12

Tendered cost - 19589.12

Cost of Completion (Lakhs) - 19589.12

Actual date of completion- 27.03.2018

Project Management Consultancy for Construction of New Administrative Block Building in BEP premesis, Dr.Rajkumar Road, Rajajinagar, Bengaluru-KRDCL

Estimated Cost (Lakhs) - 2853.00

Tendered cost - 2853.00

Cost of Completion (Lakhs) - 3272.00

Actual date of completion- 23.03.2018

Project Management Consultancy services for the works in Bangalore Circle SHDP Phase-II

Estimated Cost (Lakhs) - 14065.53

Tendered cost - 14065.53

Cost of Completion (Lakhs) - 14065.53

Actual date of completion- March 2016

Project Management Consultancy services for the works in PWD, Bangalore Circle - SHDP Phase-I

Estimated Cost (Lakhs) - 6471.29

Tendered cost - 6471.29

Cost of Completion (Lakhs) - 6471.29

Actual date of completion- Nov 2014